Rehabilitation of Maplewood Sideroad and 15th Line
Federal contribution
$461,803
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of East Zorra-Tavistock
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 17, 2009
- Construction end2 months earlyforecast Dec 31, 2010
Also in Hickson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27415 in the federal list. How to read these figures.