Upgrading of Airport Building

Earlton, Ontario

completeRegional And Local AirportsCC Top Up
Federal contribution
$12,811
Federal share33%

of $38.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Armstrong
Construction start
Jul 1, 2009(actual)
Construction end
May 31, 2010(actual)

Against the original forecast

  • Construction end10 months lateforecast Aug 1, 2009

Also in Earlton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27450 in the federal list. How to read these figures.