Improvements to the Lansdowne Drinking Water System

Lansdowne, Ontario

completeDrinking WaterCC Top Up
Federal contribution
$320,834
Federal share33%

of $962.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Dec 15, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Nov 16, 2009
  • Construction end4 weeks lateforecast Oct 31, 2010

Also in Lansdowne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27461 in the federal list. How to read these figures.