Extension of Water Distribution System
Federal contribution
$659,114
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Southwold
- Construction start
- May 28, 2010(actual)
- Construction end
- Sep 28, 2010(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Oct 28, 2010
Also in Fingal