Sechelt - Bio-Solids Management
Federal contribution
$1.6M
$1,600,000
Federal share28%
of $5.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- District of Sechelt
- Construction start
- Apr 1, 2013(actual)
- Construction end
- Mar 31, 2016(actual)