Upgrades to Gilbride Road

Thunder Bay, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$112,500
Federal share45%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Local Roads Board of Fowler
Construction start
Aug 14, 2009(actual)
Construction end
Sep 28, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 20, 2009
  • Construction end2 months earlyforecast Nov 30, 2010