Construction on Lisbonne Street in the François Leclerc Industrial Park

Saint-Augustin-de-Desmaures, Quebec

completeWastewaterCC
Federal contribution
$846,125
Federal share25%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 2, 2009
20102011
Built

Approved 4 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
May 28, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jun 15, 2009
  • Construction end17 months lateforecast Oct 16, 2009