Back to projects

Improvements to Storm Bay Road

Longbow Lake, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$45,000
Federal share45%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Nov 5, 2009(actual)
Construction end
Nov 12, 2010(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Oct 29, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27737 in the federal list. How to read these figures.