Improvements to Vankleek Hill Lagoon Sewage Treatment Plant
Federal contribution
$269,167
Federal share33%
of $807.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Champlain
- Construction start
- Nov 15, 2009(actual)
- Construction end
- Jul 31, 2011(actual)
Against the original forecast
- Construction end3 months earlyforecast Oct 31, 2011