Rehabilitation of Lakehurst Hall

Bobcaygeon, Ontario

completeRecreationCC Top Up
Federal contribution
$200,000
Federal share33%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Oct 26, 2009(actual)
Construction end
Nov 10, 2010(actual)

Against the original forecast

  • Construction end2 months lateforecast Aug 30, 2010

Also in Bobcaygeon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27802 in the federal list. How to read these figures.