Improvements to Geneva Lake Road
Federal contribution
$14,175
Federal share45%
of $31.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Local Roads Board of Hess Township
- Construction start
- Aug 1, 2009(actual)
- Construction end
- Nov 17, 2010(actual)
Against the original forecast
- Construction end8 weeks lateforecast Sep 21, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27803 in the federal list. How to read these figures.