Construction of Harrow Soccer Complex
Federal contribution
$779,167
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Essex
- Construction start
- Oct 14, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 15, 2009
Also in Essex
- Essex County Road 50 West - Paved Shoulders: Historic Scenic component of the Great Lakes Waterfront Trail$2.3M
- Reconstruction of Dunn Road$1.2M
- Reconstruction of 3rd Concession/Roseborough Road and Hanlan Street$898.8K
- McGregor Library and Community Centre$578.0K
- Upgrades to the Harrow-Colchester South Water treatment plant including Low and High Lift Pumps, Motor Control Center Panel and Microstrainer$507.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27808 in the federal list. How to read these figures.