Resurfacing of Mine Centre Road
Federal contribution
$27,738
Federal share45%
of $61.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Local Roads Board of Mine Centre
- Construction start
- Jun 10, 2010(actual)
- Construction end
- Oct 29, 2010(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Jul 26, 2010
- Construction end3 months lateforecast Aug 4, 2010