Reconstruction of Dewey Road
Federal contribution
$633,210
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Stone Mills
- Construction start
- Sep 21, 2009(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start8 months earlyforecast May 31, 2010
- Construction end4 weeks earlyforecast Oct 31, 2011