Rehabilitation of William and Mathew Streets
Federal contribution
$70,564
Federal share33%
of $211.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Rideau Lakes
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Nov 30, 2009(actual)
Also in Delta