Improvements to Howcum Lake Road
Federal contribution
$100,800
Federal share45%
of $224.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Local Roads Board of Jacques
- Construction start
- Jul 31, 2009(actual)
- Construction end
- Sep 28, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 20, 2009
- Construction end2 months earlyforecast Nov 30, 2010
Also in Thunder Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27896 in the federal list. How to read these figures.