Back to projects

Redevelopment of Lafontaine Pavilion

Perkinsfield, Ontario

completeRecreationCC Top Up
Federal contribution
$220,000
Federal share33%

of $660.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Tiny
Construction start
Jul 9, 2010(actual)
Construction end
Feb 28, 2011(actual)

Against the original forecast

  • Construction start13 months lateforecast Jun 15, 2009
  • Construction end8 weeks lateforecast Dec 31, 2010

Also in Perkinsfield

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27948 in the federal list. How to read these figures.