Revelstoke Trans-Canada Highway Water Reservoir Replacement
Federal contribution
$322,000
Federal share33%
of $966.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of Revelstoke
- Construction start
- Jan 10, 2011(actual)
- Construction end
- Oct 31, 2011(actual)
Also in Revelstoke