Back to projects

Revelstoke Trans-Canada Highway Water Reservoir Replacement

Revelstoke, British Columbia

completeDrinking WaterCC Top Up
Federal contribution
$322,000
Federal share33%

of $966.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Revelstoke
Construction start
Jan 10, 2011(actual)
Construction end
Oct 31, 2011(actual)

Also in Revelstoke