New Reservoir

Kings, Nova Scotia

completeDrinking WaterCC
Federal contribution
$252,484
Federal share33%

of $757.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2009
200920102011
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Port Williams
Construction start
Oct 1, 2009(actual)
Construction end
Mar 29, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28144 in the federal list. How to read these figures.