completeDrinking WaterCC Top Up
Federal contribution
$70,000
Federal share33%

of $210.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 11, 2010
2011
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Blaine Lake
Construction start
Nov 19, 2010(actual)
Construction end
Sep 14, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 12, 2010
  • Construction end7 weeks earlyforecast Oct 31, 2011