Water and Sewer on 1st Avenue Extension
Federal contribution
$70,000
Federal share33%
of $210.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2010
2011
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Blaine Lake
- Construction start
- Nov 19, 2010(actual)
- Construction end
- Sep 14, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 12, 2010
- Construction end7 weeks earlyforecast Oct 31, 2011
Also in Blaine Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28176 in the federal list. How to read these figures.