Waterworks Upgrade
Federal contribution
$2,363
Federal share33%
of $7.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Dafoe
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Aug 18, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2010
- Construction end5 months lateforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28233 in the federal list. How to read these figures.