Back to projects

Waterworks Upgrade

Dafoe, Saskatchewan

completeDrinking WaterCC Top Up
Federal contribution
$2,363
Federal share33%

of $7.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Dafoe
Construction start
Aug 1, 2010(actual)
Construction end
Aug 18, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2010
  • Construction end5 months lateforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28233 in the federal list. How to read these figures.