Lagoon Rehabilitation & Expansion

Riverhurst, Saskatchewan

completeWastewaterCC
Federal contribution
$160,366
Federal share33%

of $481.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
20102011201220132014
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Riverhurst
Construction start
May 22, 2012(actual)
Construction end
Jul 29, 2014(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Mar 31, 2012
  • Construction end4 weeks lateforecast Jun 30, 2014