Improvement to water treatment plant
Federal contribution
$1.4M
$1,387,500
Federal share25%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2009
201020112012
Built
Approved 7 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Thurso
- Construction start
- May 1, 2010(actual)
- Construction end
- Mar 3, 2012(actual)
Against the original forecast
- Construction start9 months lateforecast Aug 1, 2009
- Construction end4 weeks earlyforecast Mar 31, 2012
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28280 in the federal list. How to read these figures.