Water Treatment Plant Upgrade
Federal contribution
$600,249
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Vonda
- Construction start
- Mar 25, 2010(actual)
- Construction end
- Dec 21, 2011(actual)
Against the original forecast
- Construction start12 months earlyforecast Apr 1, 2011
- Construction end3 months earlyforecast Mar 31, 2012
Also in Vonda
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28284 in the federal list. How to read these figures.