Water Treatment Plant Upgrade
Federal contribution
$447,333
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 11, 2013
201420152016
Built
Approved 4 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Watrous
- Construction start
- Nov 17, 2014(actual)
- Construction end
- Feb 16, 2016(actual)
Against the original forecast
- Construction start4 months lateforecast Aug 1, 2014
- Construction end6 weeks earlyforecast Mar 31, 2016
Also in Watrous