Construct R.O Water Treatment Plant & Pipeline
Federal contribution
$357,575
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Middle Lake
- Construction start
- Dec 1, 2009(actual)
- Construction end
- Oct 25, 2011(actual)
Against the original forecast
- Construction start5 months earlyforecast May 1, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28333 in the federal list. How to read these figures.