Back to projects

Water Treatment Plant Upgrade

Leoville, Saskatchewan

completeDrinking WaterCC Top Up
Federal contribution
$54,650
Federal share33%

of $164.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Leoville
Construction start
Jan 6, 2011(actual)
Construction end
Mar 22, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast May 1, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28411 in the federal list. How to read these figures.