Reservor Expansion

Radisson, Saskatchewan

completeDrinking WaterCC
Federal contribution
$180,454
Federal share33%

of $541.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Radisson
Construction start
Sep 17, 2012(actual)
Construction end
Sep 30, 2013(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Oct 31, 2013