Back to projects

Highway 1 - Rehabilitation East of Banff Park, East of the Kananaskis River

Canmore, Alberta

completeHighways and RoadsISF
Federal contribution
$1.7M
$1,742,038
Federal share50%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Sep 15, 2009(actual)
Construction end
Jun 2, 2010(actual)

Against the original forecast

  • Construction start8 months earlyforecast May 15, 2010
  • Construction end10 months earlyforecast Mar 31, 2011

Also in Canmore

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28497 in the federal list. How to read these figures.