Back to projects

Rehabilitation of Highway 2, from Highway 679 to McLennan

McLennan, Alberta

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,123,313
Federal share50%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 1, 2010(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2010
  • Construction end5 months earlyforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28500 in the federal list. How to read these figures.