Rehabilitation of Three Hills Creek Bridge on Highway 21, 10 Kilometres South of Three Hills

Kneehill County, Alberta

completeHighways and RoadsISF
Federal contribution
$114,660
Federal share50%

of $229.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 1, 2009(actual)
Construction end
Nov 20, 2009(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2009
  • Construction end4 months earlyforecast Mar 31, 2010

Also in Kneehill County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28504 in the federal list. How to read these figures.