Resurfacing Work on Highway 556
Newell No. 4 (County), Alberta
Federal contribution
$2.1M
$2,126,531
Federal share47%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Oct 21, 2010(actual)
- Construction end
- May 16, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 15, 2010
- Construction end5 months earlyforecast Sep 30, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28507 in the federal list. How to read these figures.