Resurfacing Work on Highway 556

Newell No. 4 (County), Alberta

completeHighways and RoadsISF
Federal contribution
$2.1M
$2,126,531
Federal share47%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Oct 21, 2010(actual)
Construction end
May 16, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Sep 15, 2010
  • Construction end5 months earlyforecast Sep 30, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28507 in the federal list. How to read these figures.