Wastewater treatment

Saint-Bernard-de-Michaudville, Quebec

completeWastewaterCC
Federal contribution
$1.7M
$1,657,500
Federal share43%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 21, 2009
201020112012201320142015
Built

Approved 3 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
May 1, 2012(actual)
Construction end
Jun 30, 2015(actual)

Against the original forecast

  • Construction end6 months lateforecast Dec 31, 2014