Back to projects

Infrastructure work

Saint-Jacques-de-Leeds, Quebec

completeWastewaterCC
Federal contribution
$4.6M
$4,567,345
Federal share46%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2009
20082010201220142016
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Nov 19, 2007(actual)
Construction end
Feb 3, 2016(actual)

Against the original forecast

  • Construction start23 months earlyforecast Oct 19, 2009
  • Construction end5.3 years lateforecast Nov 1, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28640 in the federal list. How to read these figures.