Domestic sewage treatment
Federal contribution
$1.5M
$1,530,016
Federal share33%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 18, 2009
201020112012201320142015
Built
Approved 5 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Saint-David
- Construction start
- Oct 6, 2009(actual)
- Construction end
- Feb 9, 2015(actual)
Against the original forecast
- Construction start7 months earlyforecast May 1, 2010
- Construction end3.9 years lateforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28667 in the federal list. How to read these figures.