Back to projects

Resurfacing Highway 16A

Evansburg, Alberta

completeHighways and RoadsISF
Federal contribution
$237,313
Federal share44%

of $543.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 11, 2010(actual)
Construction end
Jul 30, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2010
  • Construction end8 months earlyforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28682 in the federal list. How to read these figures.