Resurfacing Highway 611
Ermineskin Cree Nation, Alberta
Federal contribution
$585,247
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Nov 1, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2010
- Construction end5 months earlyforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28693 in the federal list. How to read these figures.