Back to projects

Resurfacing Highway 1A

Chestermere, Alberta

completeHighways and RoadsISF
Federal contribution
$651,841
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 14, 2010(actual)
Construction end
Oct 28, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011

Also in Chestermere

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28699 in the federal list. How to read these figures.