Back to projects

Gibbons Sewer and Pumping Station

Gibbons, Alberta

completeWastewaterISF
Federal contribution
$1.1M
$1,061,595
Federal share18%

of $5.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Gibbons
Construction start
Feb 10, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Nov 1, 2009
  • Construction end6 weeks earlyforecast Dec 15, 2011

Also in Gibbons

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28736 in the federal list. How to read these figures.