Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Crossfield
- Construction start
- Aug 24, 2009(actual)
- Construction end
- Jul 5, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 1, 2009