Sewer Extensions
Federal contribution
$116,499
Federal share26%
of $445.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Grimshaw
- Construction start
- Jul 27, 2009(actual)
- Construction end
- Sep 3, 2009(actual)
Against the original forecast
- Construction end8 weeks earlyforecast Oct 31, 2009
Also in Grimshaw
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28759 in the federal list. How to read these figures.