South Sanitary Sewer
Federal contribution
$717,258
Federal share33%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Claresholm
- Construction start
- Feb 22, 2010(actual)
- Construction end
- Jul 23, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Mar 15, 2010
- Construction end3 months earlyforecast Oct 31, 2010
Also in Claresholm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28760 in the federal list. How to read these figures.