Infrastructure Renewal on South 1st Street
Federal contribution
$269,663
Federal share33%
of $811.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Marwayne
- Construction start
- May 31, 2010(actual)
- Construction end
- Dec 31, 2010(actual)
Also in Marwayne
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28763 in the federal list. How to read these figures.