Upgrading of Airport Road and Related Works
Federal contribution
$848,536
Federal share33%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Edson
- Construction start
- Aug 18, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 15, 2009
Also in Edson
- Highway 16 Underground Infrastructure Replacement/Upgrading$3.0M
- Expansion and Construction of Galloway Station Museum$922.2K
- Purchase of a wheelchair accessible vehicle to support transit in Edson, Alberta.$95.1K
- Public Transit Study for Edson, Alberta$45.0K
- Edson New Trail Construction - Part of Municipal Trail System$27.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28776 in the federal list. How to read these figures.