Local Roads Paving
Federal contribution
$159,418
Federal share19%
of $836.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Spring Lake
- Construction start
- Jun 2, 2010(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 3, 2010
- Construction end6 months earlyforecast Dec 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28801 in the federal list. How to read these figures.