Back to projects

Local Roads Paving

Spring Lake, Alberta

completeHighways and RoadsISF
Federal contribution
$159,418
Federal share19%

of $836.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Spring Lake
Construction start
Jun 2, 2010(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 3, 2010
  • Construction end6 months earlyforecast Dec 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28801 in the federal list. How to read these figures.