Water and Sewer Replacement in the West End of Blairmore
Federal contribution
$593,906
Federal share31%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Crowsnest Pass
- Construction start
- Feb 1, 2010(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 30, 2010
Also in Blairmore
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28860 in the federal list. How to read these figures.