51st Avenue Rehabilitation
Federal contribution
$225,358
Federal share29%
of $768.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Wabamun
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Aug 31, 2010(actual)
Against the original forecast
- Construction start8 months earlyforecast May 3, 2010
- Construction end4 months earlyforecast Dec 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28867 in the federal list. How to read these figures.