51st Avenue Rehabilitation

Wabamun, Alberta

completeHighways and RoadsISF
Federal contribution
$225,358
Federal share29%

of $768.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Wabamun
Construction start
Sep 1, 2009(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction start8 months earlyforecast May 3, 2010
  • Construction end4 months earlyforecast Dec 31, 2010