Stormwater System Improvements

Taber, Alberta

completeWastewaterISF
Federal contribution
$2.3M
$2,344,686
Federal share26%

of $8.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Taber
Construction start
Apr 12, 2010(actual)
Construction end
Sep 15, 2011(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast May 1, 2010
  • Construction end7 weeks earlyforecast Oct 31, 2011

Also in Taber

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28879 in the federal list. How to read these figures.