Sewage Lagoon Relocation

Vulcan, Alberta

completeWastewaterISF
Federal contribution
$1.9M
$1,909,607
Federal share29%

of $6.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Vulcan
Construction start
Jul 27, 2010(actual)
Construction end
Oct 28, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 28, 2010