Sewage Lagoon Relocation
Federal contribution
$1.9M
$1,909,607
Federal share29%
of $6.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Vulcan
- Construction start
- Jul 27, 2010(actual)
- Construction end
- Oct 28, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 28, 2010
Also in Vulcan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28884 in the federal list. How to read these figures.