Brobble Road Reconstruction
Federal contribution
$108,070
Federal share25%
of $437.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipal District of Willow Creek
- Construction start
- Sep 30, 2010(actual)
- Construction end
- Mar 25, 2011(actual)
Against the original forecast
- Construction end3 months earlyforecast Jun 30, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28909 in the federal list. How to read these figures.